Chapter 20: Acceptance Testing
Many systems and products include complete documentation, covering
acceptance testing. Individual circuit packs may have their own segmented "card-level"
tests, but after everything is hooked up end-to-end, a real-world test must be
made to verify that the entire system is fully ready to support live traffic.
For many T1 transmission systems, the bit error rate tests use QRSS (Quasi
Random Signal Sequence pattern). There may be a different test strategy for each
different type of T1 product, but a few common strategies are suggested in the
following figure, Figure 11. The exact error-free performance requirements vary
from one location to another, but if there are no other guidelines to use, start
with BER of 10-8 or better if the live traffic contains only voice
channels. If data channels are present, try to start with BER of 10-10
or better. Over some facilities, still better performance can be measured, but
it takes a tremendous amount of time. For normal telco transmission facilities,
acceptance tests are commonly run for periods of a few hours at most. It is most
important to record all information regarding the acceptance tests. It is good
form to include a copy of the product practice that lists the test procedure
along with the actual results and a sketch of how the tests were run. Acceptance
tests should be kept on file in every central office or equipment room.